Lachenmeire & New Line Installation

We were recently tasked with the removal of outdated equipment and the installation of a new Lachenmeire system as part of a production line upgrade. With limited space, tight deadlines, and strict safety protocols in place, this project required careful planning and round-the-clock coordination. Our team worked tirelessly to ensure a smooth and efficient installation.

For this project, we:

  • Safely removed existing equipment and security fencing
  • Maintained operational integrity of surrounding processes during removal
  • Navigated extremely tight working space using carefully selected lifting plant
  • Enforced strict personnel/plant segregation throughout the works
  • Installed the new Lachenmeire and production line equipment
  • Worked 24/7 in coordination with OEM support to meet the project deadline

The biggest challenges for this project were the tight physical constraints of the site, limited access for lifting equipment, and a very short installation window. We overcame these challenges by operating a 24/7 schedule, working in close coordination with the OEM’s technical team, and maintaining strict site controls to ensure safety and efficiency at every stage of the project to ensure a successful outcome.

Did you know?

Many large-scale equipment installs are now carried out during 'live changeovers', where surrounding operations must continue running — adding major complexity to planning and safety.

© 2025 Diamond Responsive Engineering Ltd. All rights reserved | Registered in England & Wales. Company Number: 05927511 | Registered Address: Diamond Business Park, Butterthwaite Lane, Ecclesfield, Yorkshire, S35 9WA

Website by Ronan Smith